Six Sigma Green Belt Certification Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for your Six Sigma Green Belt Certification Exam with confidence. This exam is a critical step in enhancing your career prospects in quality management and process improvement. Tackle interactive questions with hints and explanations and ace your certification!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following tools is used to identify potential events and contingencies for an implementation plan?

  1. Pert chart

  2. Process decision program chart

  3. Fishbone diagram

  4. House of quality

The correct answer is: Process decision program chart

The tool used to identify potential events and contingencies for an implementation plan is the Process Decision Program Chart (PDPC). This tool is specifically designed to help teams anticipate potential problems or events that could affect a project and allows for the planning of contingencies in response to those anticipated issues. The PDPC visualizes the events and their potential results in a structured format. By laying out the main process steps and branching out possible contingencies, teams can systematically evaluate risks and necessary responses. This proactive approach is critical in project planning, as it enables organizations to prepare for various scenarios, thereby enhancing the likelihood of successful implementation. In contrast, the other tools mentioned serve different purposes. A Pert chart is primarily used for project scheduling and managing the timeline of tasks, the Fishbone diagram is employed for identifying root causes of problems, and the House of Quality focuses on defining customer requirements and translating those into engineering and operational specifications. Each of these tools has its unique applications but does not specifically address the identification of events and contingencies like the PDPC does.